wareHOUSE(1) 1900 greenwood PROJECT UPDATE 2.11.2016



warehouse(1)
1900 GREENWOOD
Evanston, Illinois 60201
adas/spatz properties

PROJECT UPDATE (2.11.2016):


Progress in 2016 has been on schedule. The PLUMBING, ELECTRICAL, HVAC and CARPENTRY contractors hit their marks. CITY INSPECTIONS were uneventful. The jobsite is two contiguous buildings. This allowed Matt to schedule the project so the trades move from south to north making it possible for the INSULATION, DRYWALL and PAINTING contractors to be on site at the same time as the other trades mentioned above. 


Presently, the DRYWALL contractor is finishing up at the north end and adjacent service corridor. The PAINTING preparation and priming just started. 


NEXT…the HVAC contractor starts at the north end chasing the PAINTER and so on. We are early into the finishing phase.


enjoy the photos and video links below, andy

PLUMBING: ziggy is finishing up the overhead 1.5" water feed in the service corridor. these pipes will receive insulating wrap later in the project.
ELECTRICAL: recessed fixtures are being "layed out" now that this mezzanine has been framed.

ELECTRICAL: service is finished, ready for COMED metering.
CARPENTRY: mezzanine in unit 3 is ready for sound insulation.
CARPENTRY & ELECTRICAL: wire is being pulled to the recessed fixture. ready for sound insulation.
CITY OF EVANSTON: Claude and Matt have just completed the rough electrical inspection for units 6-9.

CITY OF EVANSTON: Howard and Matt have just completed the rough plumbing inspection for units 6-9.
CARPENTRY: wood frames/doors are installed prior to drywall due to detailing.
INSULATION: blown in blanket insulation for the exterior frame walls is pumped from the truck to the appropriate location.
INSULATION: 2x6 fiberglass ECO sound insulation is installed in all interior walls.
DRYWALL: material delivery in process.
DRYWALL: unit 8 hanging in process.
DRYWALL: unit 8 hanging in process. all material is glued/screwed into place.
DRYWALL: unit 9 hanging in process. almost ready to start taping. unit 9 is at the north end of the building. the structural steel shall be left exposed.
DRYWALL: taping in unit 8 has started.
DRYWALL: taping in unit 9. julio applies the 2nd of 3 applications of joint compound.
ROOF PENETRATIONS: On a snowless January weekend with temperatures above freezing, we had (38) 4" holes to be cored for the PLUMBING, ELECTRICAL & HVAC contractors. in places, we cored 9" through concrete, rigid insulation and the original roof membrane. This operation is sequenced after the roof has been installed and then flash into place by the ROOFING contractor.
ROOF PENETRATIONS: the white tube supplies suction to the drill platform during coring.
ROOF PENETRATIONS: ready for the PLUMBER to complete the waste line vent through the roof.
ROOF PENETRATIONS: water heater flashing is heat welded to the TPO roof membrane.
ROOF PENETRATIONS: ELECTRICAL flashing in process.
DRYWALL: taping continues in unit 8.
DRYWALL: taping continues in unit 3...almost ready for priming by the PAINTER.
PAINTER: bathroom and utility rooms are being primed at north end (unit 8).
DRYWALL: taping continues in unit 5.
DRYWALL: jesus, our drywall contractor does an excellent job.
DRYWALL: taping continues in unit 5.
PLUMBING: NICOR has installed their meters for units 6-9 which are now being tied into the system. the yellow tubing supplies gas to our temporary unit heaters in the service corridor.
PAINTING: masonry walls and concrete floor have been masked prior to starting ceiling priming/painting at the north end of the building (unit 9).
PAINTING: masonry walls and concrete floor have been masked prior to starting ceiling priming/painting at the north end of the building (unit 9).
PAINTING: steel structure is scrapped and cleaned with compressed air prior to priming. notice the bits of loose concrete on the floor. 

PAINTING: steel structure is being primed. finished paint to follow.