Friday, April 13, 2018

warehouse(2) 2113 greenleaf (project update) 4.12.2018


wareHOUSE(2)
2113 GREENLEAF
Evanston, Illinois 60201
adas/spatz properties

PROJECT UPDATE (04.12.2018):


Concurrently, multiple trades continue the north to south rotation maintaining our project schedule. This project update groups our photos by trade to make the controlled chaos easier to follow.

- CARPETNTRY (cabinet installation, prep for all other trades)
- ORNAMENTAL IRON (completion of the steel stairs)
- PAINTING (priming, finished coat #1, spraying)
- CERAMIC TILE (bathroom wall tile & kitchen backsplash installation)
- HVAC (ductwork installation)
- FINISHED FLOORS (concrete floor prep, epoxy finished coating)


NEXT, exterior sun screens, site work + continuation of finishing the interiors with ELECTRICAL being added to the mix
…progress

andy


CARPENTRY: cabinet installation.
CARPENTRY: cabinet installation.
ORNAMENTAL IRON: matt checks layout.
ORNAMENTAL IRON: jose welds stair treads.
ORNAMENTAL IRON: ready for railings.
ORNAMENTAL IRON: railings installed in this unit. 
ORNAMENTAL IRON: railings being installed.
ORNAMENTAL IRON: railings installed on stair, wall and mezzanine.
LOFT VIEW to 1st level.
PAINTING: priming.
PAINTING: priming.
PAINTING: 1st finished coat. special colors for a special client.
PAINTING: marek readies trim for carpenters.
CERAMIC TILE: we have worked with arben over 20 years.
HVAC: ductwork installation in progress.
HVAC: ductwork installation in progress.
HVAC: ductwork installation in progress.
FINISHED FLOORS: step 1, concrete is thoroughly scrubbed. clemente & mario have been with us 15+ years.
FINISHED FLOORS: step 2, coat #1 of water based low VOC epoxy. 30 mils when completed.
FINISHED FLOORS: step 1,coat #1 completed.
PAINTING: lukasz takes a break from spraying the ceilings in the service corridor. we have a 15 year history. 

 FINISHED FLOORS: step 2, coat #1 of water based low VOC epoxy. 30 mils when completed.