Wednesday, August 10, 2016

wareHOUSE(1) 1900 greenwood, PROJECT UPDATE 8.10.2016



wareHOUSE(1)

1900 GREENWOOD
Evanston, IL 60201
adas/spatz properties




Our new tenants have moved in and are getting settled. the short video below gives you a brief overview of the services we provide making this process LESS painful. DONE is good.



Thanks for watching. Special thanks to Julia who has produced our last few videos.  

andy

PROJECT UPDATE (08.10.2016):

Friday, July 29, 2016

wareHOUSE(1) 1900 greenwood, PROJECT UPDATE 8.10.2016



wareHOUSE(1)

1900 GREENWOOD
Evanston, IL 60201
adas/spatz properties




PROJECT UPDATE (07.29.2016):





I have been lax with my UPDATE…just busy.

ALL TRADES were 100% complete the first week in July with our FCO (final occupancy permit) acquired shortly thereafter. 7 of 9 units have been leased/occupied.



Enjoy the photos and video links below.


andy

P.S. Matt and I are already on to our next project slated for occupancy late 2017…STAY TUNED. 

CERAMIC TILE: arben is installing kitchen backsplash tile.
CERAMIC TILE: full height splash, DONE...ready for appliances.
READY for appliances in unit 1.
CARPET: we have been working with ken for more than 30 years.
CONCRETE: pouring entry and ramp slabs to units 1-3.
CONCRETE: slabs complete.
PAINTING: ted's finishing up the service corridor.
PLUMBING: slavek is installing a lav faucet.
ORNAMENTAL IRON/CARPENTERS: our aluminum/steel fabricator teams up with the CARPENTERS to complete the exterior entry canopies and skin ...each has certain required skills...lotsa fotos to follow.
ORNAMENTAL IRON/CARPENTERS: aluminum armatures are being attached.
ORNAMENTAL IRON/CARPENTERS: aluminum armatures are being attached.
ORNAMENTAL IRON/CARPENTERS: aluminum armatures are being attached.
ORNAMENTAL IRON/CARPENTERS: aluminum armatures are being attached.
ORNAMENTAL IRON/CARPENTERS: aluminum armatures are being attached.
ORNAMENTAL IRON/CARPENTERS: aluminum armatures are being attached.
ORNAMENTAL IRON/CARPENTERS: aluminum armatures are being attached. final positions have been set and are welded into place.
ORNAMENTAL IRON/CARPENTERS: aluminum armatures are being attached. almost ready for "skin".
ORNAMENTAL IRON/CARPENTERS: aluminum armatures are being "skinned". vertical surfaces receive 1/8"  aluminum sheet.
ORNAMENTAL IRON/CARPENTERS: aluminum armatures are being attached.
ORNAMENTAL IRON/CARPENTERS: aluminum canopy armatures receive perforated aluminum sheet which allows water to pass through. this prevents waterproofing problems at the brick wall. exterior lighting is integrated into the armature with the pipe used as electrical conduit.
ORNAMENTAL IRON/CARPENTERS: aluminum canopy armatures receive perforated aluminum sheet.
ORNAMENTAL IRON/CARPENTERS: aluminum wall armature receives 1/8' solid aluminum sheet.
ORNAMENTAL IRON/CARPENTERS: aluminum canopy armatures receive perforated aluminum sheet.
ORNAMENTAL IRON/CARPENTERS: aluminum exterior is about DONE.
ORNAMENTAL IRON/CARPENTERS: aluminum exterior is NOW DONE.
CONCRETE: removing the old concrete parking area. new parking lot prep to follow.
CONCRETE: parking area in full swing.
CONCRETE: parking area being poured.
READY for occupancy...on to NEXT.

ORNAMENTAL IRON/CARPENTERS: aluminum canopy armature install.




Thursday, May 5, 2016

wareHOUSE(1) 1900 greenwood, PROJECT UPDATE 5.5.2016



warehouse(1)
1900 GREENWOOD
Evanston, Illinois 60201
adas/spatz properties




ORNAMENTAL IRON, HVAC, PAINTING, FLOOR finishing (low VOC epoxy over existing concrete first floor) and now CABINETRY install continue the south to north rotation. The CONCRETE contractor is about 70% complete with units 1- 3 entries, exterior ADA ramp and aluminum skin related concrete elements. The CEMENT PLASTER finished skin at the dodge avenue entries has been started/completed. The ELECTRICAL contractor is now also on the job installing overhead lighting and ceiling fans. GRANITE counter tops have been installed in units 6-9 bathrooms and kitchens.


NEXT…CONCRETE at the north end continues, TILE contractor returns next week, ELECTRICAL, HVAC, PAINTING, EPOXY FLOOR, CARPENTRY and CABINETRY move into units 1-5. The ORNAMENTAL IRON contractor will start the exterior skin’s aluminum armature in the next 10 days…it’s crowded.


Enjoy the photos and video links below.



andy



ORNAMENTAL IRON: matt, jose & gabino start stair alignment prior to permanent attachment.
ORNAMENTAL IRON: guard/handrail is being welded in unit 4.
ORNAMENTAL IRON: weld at handrail is being "finished".
ORNAMENTAL IRON: pre-grinding handrail turn.
ORNAMENTAL IRON: unit 1 wall handrail has been attached. drywall is being installed.
HVAC: igor is responsible for the exposed ductwork installation as he has for the last dozen years. always a near perfect job.
HVAC: the finished product.
HVAC: supply riser in unit 4, notice the interior unistrut channel fastening system attachment to the bar joist.
HVAC: exposed duct run transition.
HVAC: the finished product.
PAINTING: concrete ceiling in the re-purposed loading dock is being prepared for paint.
PAINTING: lukasz is setting up a support system for finishing the hollow metal door to be installed off the service corridor.
PAINTING: set up and ready to go.
PAINTING: hollow metal doors/frames in process.
 FINISHED FLOOR (epoxy): mario power scrubs the concrete prior to installing the 30 mil low VOC water based epoxy system.
FINISHED FLOOR (epoxy): deep depressions are pre-filled and allowed to dry for 24 hours prior to starting the 2 coat finishing process.
FINISHED FLOOR (epoxy): first coat is being applied. we use a standard 9" roller in lieu of the larger floor roller since it's easier to control and thus give us a better end product.
FINISHED FLOOR (epoxy): unit 9 is complete.
CABINETRY: ales is delivering our custom designed/fabricated cabinet. we have been working together for 8 years.
CABINETRY: cabinet installation in process.
CABINETRY: tomek & marek are getting close to completion in this unit. the cabinet door are a natural finish, horizontal grain rift oak veneer 3/4" MDF board. the boxes are fabricated from 3/4" black MDF and the sink base bottom is laminated plastic for longevity.
CABINETRY: this kitchen is ready for the granite countertops.
CABINETRY: another unit is almost complete.
CABINETRY: kris & janusz are cutting countertop templates for the granite fabricator to insure a proper fit.
ELECTRICAL: the electrical contractors are installing the kitchen light track.
STUCCO (cement plaster): arturo is finishing up a recessed entry off dodge.
CONCRETE: footings for ADA ramp have been poured.
CONCRETE: walls all almost framed. we opted to do this in 2 sections...one underground and one that is exposed above grade.
CONCRETE: underground ramp walls have been poured.
CONCRETE: above graded walls being framed and steel reinforcing bars being installed.

CONCRETE: the guys.
CONCRETE: ramp walls have been poured and stripped.
CONCRETE: backfilling
MODEL: looking SW from dodge avenue.