warehouse(1)
1900 GREENWOOD
Evanston, Illinois 60201
adas/spatz
properties
ORNAMENTAL
IRON, HVAC, PAINTING, FLOOR finishing (low VOC epoxy over existing concrete
first floor) and now CABINETRY install continue the south to north rotation.
The CONCRETE contractor is about 70% complete with units 1- 3 entries, exterior
ADA ramp and aluminum skin related concrete elements. The CEMENT PLASTER
finished skin at the dodge avenue entries has been started/completed. The
ELECTRICAL contractor is now also on the job installing overhead lighting and
ceiling fans. GRANITE counter tops have been installed in units 6-9 bathrooms
and kitchens.
NEXT…CONCRETE
at the north end continues, TILE contractor returns next week, ELECTRICAL,
HVAC, PAINTING, EPOXY FLOOR, CARPENTRY and CABINETRY move into units 1-5. The
ORNAMENTAL IRON contractor will start the exterior skin’s aluminum armature in
the next 10 days…it’s crowded.
Enjoy the photos and video links below.
andy