SHOP(studios)
adas/spatz properties
PROJECT UPDATE (4.19.2010):
Finishing Up
The plumbing, electrical, and HVAC contractors are 100%. The CARPENTERS have installed the wood trim, loft rails and interior doors. FINSIHED FLOORS are also complete…the water based epoxy floor stain/finish has been applied over the concrete first floor and the lofts now have CARPET. The METAL FABRICATORS have finished their jobs on the façade and the CONCRETE parking area is vehicle ready.
NEXT time, finished pics…
PS: we just started leasing. 2 out of 5 units are spoken for. I think the units are aggressively priced ($1,250 -$1,575 per month)…so if you know of someone, please PASS ON this info.
THANKS ANDY