SKYlofts
1629
OAK
evanston, IL 60201
adas/spatz properties
PROJECT
UPDATE (10.7.2013):
It's been
12 weeks since the existing 2 story frame building was demolished. We are a
week ahead of schedule (sure to change) due to most material needing only to be
assembled as opposed to being cut/assembled. This is expedited by matt's layout
and the accuracy of the concrete installation. Our
present focus is getting weather tight for winter.
NEXT…window
wall framing with exterior sheathing starting next week.
DON’T
MOVE THAT DIAL
10.7.2013: looking E |
MODEL: looking NE |
10.7.2013: looking NE |
MODEL: looking NW |
10.7.2013: looking NW |
9.19.2013: looking NW (eight stories up) |