AFZ+3 (2nd
floor redux)
604-606 Davis
Evanston, Illinois 60201
adas/spatz
properties
PROJECT UPDATE
(12.14.2011):
WINTER
READY, The CARPENTERS have been
busy erecting the building’s shell which is now 100% complete. Windows have
been measured and ordered. The ROOFING CONTRACTOR has also installed the single
ply modified roof/4”rigid insulation system. We are enclosed/watertight and now
able to heat the interior as needed. The roof will be completed in spring after
the exterior metal skin and roof drainage system have been installed.
The
CARPENTERS are also nearly complete with the interior framing and the
MECHANICAL TRADES will start their portion of the project shortly.
ANDY
(enjoy
the photos & video)
CARPENTRY: framing on the davis st. façade continues. The “boom lift”
makes the job safer and quicker. Radek is
working on the east window openings.
CARPENTRY: the layout needs to be PERFECT for the multiple
intersections to finish as designed. attribute this to the
skill/patience of matt & the carpenters.
CARPENTRY: the layout needs to be PERFECT for the multiple
intersections to finish as designed. attribute this to the
skill/patience of matt & the carpenters.
CARPENTRY: interior view of davis street façade framing looking E.
CARPENTRY: the upper portion of the projected window elements are
complete and being sheathed with ½” cdx
plywood. The boom lift makes this “doable”. Once this is done the lower portion will be
completed.
CARPENTRY: the upper portions
of the projected window elements have been wrapped.ice
& watershield (black material) is used on the sloped wall that we treat as
a roof. tyvek
house wrap is used on the vertical surfaces and cover the window openings until the windows are installed in
conjunction with the exterior metal skin.
CARPENTRY: framing for the lower portion of the projected window
elements is in process.
CARPENTRY: kris & casey work from the street canopy scaffolding.
CARPENTRY: the framing for lower portion of the projected window
elements is ready to be wrapped. Looking SE
MODEL: N elevation.
CARPENTRY: concurrently with the davis st. façade, the rear addition
was being built.the framing is a bit complex due
to cantilevered roof overhangs on two sides.
CARPENTRY: engineered wood beams are used for the major structural
members to maintain a thin, 5 ½” (2x6)
edge profile. Engineered wood is also used to create the south (alley) overhang. hey are
“sistered” to the 2x12 roof joists.
CARPENTRY: 5 1/2” engineered wood overhang on south elevation. These
members will be cut to a curved shape
during the roof deck installation.
CARPENTRY: 5 ½” engineered wood is “sistered” to the 2x12 roof
joists, ¾” roof deck is being installed.
CARPENTRY: it took 4 men to push the 2x12 band board into its curved shape . it will be cut/planed to
follow the roof plane.
CARPENTRY: 2x12 curved band board is cut with a sawzaw by jacob on the
right, then planed flush by tomek to
follow the roof plane so the roof deck can becompleted prior to roofing.
CARPENTRY: roof deck can now be completed.
CARPENTRY: another crew is working on the 2x6 sloped wall framing.
CARPENTRY: another crew is working on (6) new skylight openings.
notice that roofing material has been
delivered (back of picture). It was a race to get theproject enclosed and waterproof.
that’s matt on the right doing my job…plugging in power cords.
ROOFING: (2) 4’x8’x2” poliso rigid insulation panels are
mechanically fastened thru the existing roof/insulation
system into the roof deck. a self-stick base sheet follows with the single ply torch applied,
modified bitumen membrane. steve is waterproofing today’s stopping point so water
can’t get under the newly installed roofing system.
CARPENTRY: naz is cutting out the new skylight openings. this is done
AFTER the new openings are waterproof.
ROOFING: first female roofer on any of our projects.
ROOFING: naz is preparing the temporary “leader box” which will be
replaced with an aluminum one during the
exterior skin process. a toilet flange has been installed/caulked into a plastic
waste basket bottom and clamped to 4” flexiblenon-perforated drain pipe…rube
goldberg would be proud.
ROOFING: eric is waterproofing the davis st. parapet.
CARPENTRY: the rear addition sloped wall framing is complete, next the
south window wall.
CARPENTRY: framing the south window wall.
CARPENTRY: south window wall is framed. ½” cdx plywood sheathing is
being installed.
CARPENTRY: interior of the rear addition. plywood sheathing being
installed.
CARPENTRY: plywood sheathing is nearly complete. the boom lift again
makes working in a tight spot safe and
easier. The thin wood members over the window openings are to keep the tyvek
wrap from being ripped by the wind until the windows are installed..
CARPENTRY: plywood sheathing is beings installed by tomek & jacob.
CARPENTRY: the rear addition is wrapped as we did the davis st. façade
elevation.
MODEL: S elevation
No comments:
Post a Comment