AFZ+3 (2nd
floor redux)
604-606 Davis
Evanston, Illinois 60201
adas/spatz
properties
PROJECT UPDATE
(11.17.2011):
The
STRUCTURAL STEEL frame is in place and the CARPENTERS are busy erecting the
building’s shell and switch to interior framing on inclement days. ROOFING is
scheduled to start at the end of the week and we will work through the weekend.
Hopefully the weather will “cooperate” just enough so we remain on schedule and
are enclosed/watertight before WINTER arrives.
ANDY
(enjoy
the photos)
CARPENTRY: the cantilevered
microlams and 2x6 joists are in place, ready for wall framing(looking
SW)
CARPENTRY: kris & radek are framing the 2x6 slopped wall on the
west projection. 2x4 blocks are used to maintain 24” spacing
since “gravity” wants these members to “rotate”
CARPENTRY: a detail of the eastern most stud in the slopped wall (see
photo below)
CARPENTRY: the western projection has been roughed out and work has
begun on the next one (looking south). The
articulated arm lift really helps radek be precise
MODEL: (looking south)
CARPENTRY: matt, kris & radek work out this corner so the finishedskin intersects at a point
CONCRETE: the piers and bollards are ready for the 2nd
floor additions structural steel frame
STEEL: the 1st beam is craned into place
STEEL: miguel drills the existing masonry wall to receive
¾” sleeve anchors that are imbedded in
epoxy. matt stabilizes the column
STEEL: the roof beam is hoisted into place with the columns
attached and is then bolted to the beam
below (looking NE)
MODEL: rear 2nd floor addition (looking NE)
CARPENTRY: tomek, kuba & matt are laying out the first floor
joist. the masonry wall on the left is doing
the “cha cha” making this a bit more difficult…typical of adaptive
reuse projects
CARPENTRY: radek is getting ready to move the next floor joist
CARPENTRY: (2)2x12’s are used every 2’ due to the long span. 2’
spacing makes it easier to work between
joists as opposed to 1’-4”.
CARPENTRY: we knew that this building was originally 1 story with a 2nd
floor addition.in the 1950’s here was a fire on the 2nd
floor and the wood framing was replaced with steel trusses. we also found that a new raised floor was
built on top of the original roof deck. we added the steel rods 4’-0” oc to tie our new addition
solidly into (2) floor joist to the left
STEEL: 2”x 2” steel angles tie the new roof structure to 2 rows of
the existing trusses
CARPENTRY: the additions floor framing is nearly complete
CARPENTRY: the additions floor framing is nearly complete
CARPENTRY: the additions floor framing is nearly complete
CARPENTRY: interior partitions are built on rainy days, our focus is
getting a new roof on before winter
STEEL: the davis street window wall was not built as we thought,
hence we needed a plan “b” in supporting the 2 projections.
we opened up the roof to confirm the beam size so we could calculate the stress of adding
additional forces to it by hanging micolams from it (see the 1st photo).
the beam was strong enough
STEEL: matt & kris are working with jose & riccardo on the first of 4
hangers consisting of (2) ¾” rods. (1) rod is
sufficient, but (2) are easier to connect
STEEL: kris is aligning the rod for cutting prior to welding
STEEL: the first rod is welded to the steel tab…7 more to go
CARPENTRY: the overhang framing on the east projection has been
started (looking SW)
MODEL: (looking SW)
steel
frame + laying out 2nd floor addition floor joists
2ND
floor addition progress
steel
hanging rod installation
No comments:
Post a Comment