wareHOUSE(2)
|
2113 GREENLEAF
evanston, IL
60202
|
adas/spatz
properties
|
PROJECT
UPDATE (9.21.2017):
All underground
PLUMBING inspections were completed by the City. Interior CONCRETE slabs, miscellaneous
piers/infill walls have also been poured. It’s a go for the CARPENTERS to
start interior partitions, however their focus has been to finish operations required
for other trades to start. The exterior sheathing for the EIFS contractor, SKYLIGHT/HVAC
roof curbs and other pre-ROOFING prep has been completed. Concurrently, the
interior/exterior MASONRY walls are 99% and the pre finish coat EFIS installation
is also nearly done.
ROOFING work
has just started. SKYLIGHTS have been ordered and WINDOWS will follow suit
within a week. It’s always a fight to get enclosed
and water tight prior to winter.
*MATT has further
revised the projects critical path which now puts us 3 weeks ahead of
schedule. This has been facilitated by the building’s configuration which
gives multiple trades room to work simultaneous and efficient.
NEXT…ROOFING,
SKYLIGHTS & more of same.
Enjoy the
photos and video…ANDY
|
CARPENTRY: densglas sheathing (yellow board) is nearly complete. EIFS to follow |
PLUMBING: underground piping inspected and ready for backfill |
CONCRETE: backfill in progress |
CONCRETE: #5 rod, wire mesh & 4 mil plastic installed, prepped for concrete in west addition |
CONCRETE: tall warehouse backfill is graded. #5 rod, wire mesh and plastic to follow |
CONCRETE: ready mix truck pours material into pumping bin |
CONCRETE: west addition slab being poured and finished |
CONCRETE: #5 rods tie new slab to existing in tall warehouse |
CONCRETE: phase 2 of west warehouse being poured. the rear section was complete the day before |
CONCRETE: finishing slab in the west warehouse |
CONCRETE: matt & fermin are contemplating tomorrow slab pour in tall warehouse |
CONCRETE: finishing up the west warehouse and service entry |
CONCRETE: matt & kris are locating a bath floor drain |
CONCRETE: joints are added a day or 2 after pouring slab |
CONCRETE: tall warehouse is ready for the carpenters |
MASONRY: this wall was built concurrently with CONCRETE slab installation at the opposite end of the project |
MASONRY: interior wall continues in unit 1 |
MASONRY: unit 1 interior wall is nearly complete |
MASONRY: stepan reworks the parapet |
MASONRY: aramis is repairing a glass block window |
CARPENTRY: aluminum outriggers are being installed to tie the sunscreen to the existing structure |
CARPENTRY: aluminum outriggers |
CARPENTRY: outrigger is fastened to the existing structural system |
CARPENTRY: MORE lumber is stocked |
EIFS: densglass sheathing joints are taped, rolled on waterproof air barrier to follow |
EIFS: waterproof air barrier has been installed, the 1.5" polystyrene STO system insulation is in process |
MASONRY & EIFS: work continues |
EIFS: STO system installation continues |
EIFS: looking NW. STO system finish coat will be installed in spring 2018 |
MODEL: looking NW |
CARPENTRY: interior framing begins, west warehouse |
CARPENTRY: typical bathroom/utility pod |
CARPENTRY: kris and tomek begin a typical 4'x8' skylight curb installation. skylights are located per plan, lasered up to corrugated metal deck, pilot holes drilled for corners. |
CARPENTRY: 2x4 plates are screwed from the bottom up to minimize ceiling mess |
CARPENTRY: curb wall in progress |
CARPENTRY: metal deck being removed above |
CARPENTRY: HVAC curb for roof top unit.. fabricated dimensions being confirmed |
CARPENTRY: skylight/HVAC curbs ready for ROOFING. roofing material has been delivered |
ROOFING: next... |
CONCRETE slab install
CONCRETE slab finishing