AFZ+3 (2nd
floor redux)
604-606 Davis
Evanston, Illinois 60201
adas/spatz
properties
PROJECT UPDATE (7.15.2012:
ALL
DONE.
we
were 100% complete at the end of may and fully occupied june 1st.
SORRY it took this long to send out this project update, but we have been “good
busy”. finished project update to
follow, shortly.
ANDY
(enjoy
the pics & video)
CARPENTRY: kasey is working on wood base.
CARPENTRY: kris & kasey are installing the rear hollow metal entry
door/frame.
PLUMBING: stainless steel lav trim is being installed. chrome pipe is
used since it’s exposed.
ORNAMENTAL IRON: matt is reviewing the installation of unit 5’s aluminum
balcony armature with humberto & jose. The
scissor lift is used for temporary support.
ORNAMENTAL IRON: the aluminum armature is attached to the masonry wall with
sleeve anchors by juan. jose is welding the
“offset” section to an aluminum plate that has already been sleeve anchored.
ORNAMENTAL IRON: completed “maintenance free” platform and rail…85% recycled aluminum.
HARDWOOD FLOOR: floors are sanded, then finished with a low VOC“ shopping center” grade finish by
BOMA. We used an unstained natural finish to shorten drying time and ease
future maintenance. 2 coats of finish are applied prior to covering with kraft
paper. a 3rd coat will be applied after painting.
HARDWOOD FLOOR/PAINT: floors have been finished and are in the process of being
covered. walls have be meticulously prepped
for final finish coat.
CARPENTRY: during the interior finishing process, the carpenters have
been working on the exterior metal skin. the 1/8” aluminum
plate panels are nearing completion with the 18" aluminum standing seam panels to follow on the
unfinished section. we have previously installed “ice & water shield” on the sloped section (black) and a
tyvek “similar” on the other sections (white).
CARPENTRY: standing seam panels are being applied. panels are left
long and then trimmed to get a straight bottom edge.
CARPENTRY: tomek is scoring the overhanging panels with
a utility knife prior to bending/breaking. the aluminum will snap after
3 or 4 back/forth bends speeding up installation.
CARPENTRY: moving right along…the sloped panels overlap the vertical
pieces which are installed first and bent over the sloped plane. polyurethane adhesive caulk is used underneath
as not to be seen an thoroughly waterproof the intersection.
ORNAMENTAL IRON: meanwhile in the back…unit 5’s balcony has been followed by
the exit stair. unlike the balcony, steel needs
to be used for strength and will need to be painted. jose is tack welding the stair treads to the
stringers. they will be continuously welded once all the treads have been installed and
adjusted.
ORNAMENTAL IRON: humberto is “sorting out” the installation?
ORNAMENTAL IRON: the treads are in place and the guard rail is in process.
ORNAMENTAL IRON: the adjacent masonry party wall is very uneven. matt, jose
and renaldo are working out the “stand offs” so
this rail will be straight.
CARPENTRY: kris is installing insulation on the water
supply lines or they will drip from condensation.note they plastic bag over the
CO2/smoke detector. during construction the sensors need to be kept dust free to avoid future
false positives.
EXCAVATION/CONCRETE: the previous “beat” parking area
is being removed. the concrete will be recycled.
EXCAVATION/CONCRETE: parking lot is being filled and
graded.
EXCAVATION/CONCRETE: we got started pouring a bit
late. finishing was completed “under the lights”.
CARPETNRY: back on davis street…panel overlaps have been
waterproofed. this job would have been extremely difficult without
the lift.
CARPENTRY: aluminum coping is being installed at the
roof to flash that edge and will be counterflashed to the
roof with modified bitumen later. the 1/8" panels are being cleaned on the left with the lift.
CARPENTRY: aluminum coping is nearly complete.
PAINT: the steel stair at the rear is being prepped for paint.
CARPENTRY: the 1/8” aluminum plate is being cleaned.
PAINT: lukacz & rafal are finish coating the interior of unit 5.
PAINT: the stair is being painted using a DTM (direct to metal) oil base
product by benjamin moore, it’s more
durable than “greener” water based products and ultimately greener over time.
PAINT: the scaffolding is GONE and all that’s left is painting the 1st
floor soffit.