Monday, November 16, 2009


PROJECT UPDATE (11.9.2009):


Pre-drywall construction continues.

The carpenters have the unit interiors 95% framed as well as the protruding skylight curbs and exterior mechanical flashings. The roof is 100% ready for the waterproof membrane. Most of the windows and glass unit entry doors have been installed. NEXT…exterior fenestration. The electricians instead of the plumbers were the first mechanical trade to start their interior work. The designated “pipe chase” location for their electrical panels/feeds and communication conduit required the switch. Adaptive re-use is different than new construction. Exterior service work is nearly complete and wire has been pulled to the panels. Individual units will be started as soon as matt returns from maternity assistance leave, later this week. The plumbers zoomed through most of the waste, vent and water piping. Once the roof is finished, they will return to tie in the water piping to the service, complete the vent piping through the roof and tie in the roof drain system to the city sewer. Pipe chase related HVAC work has also been completed. The air conditioning line sets have been installed. Roof penetrations for the furnace and water heater flues have been located for each unit. NEXT TIME… the roof insulation/waterproofing system, wrapping up the mechanical trades and the exterior skin.

ANDY (enjoy the fotos)



MASONS touch-up glass block @ unit entries


CARPENTERS
are getting ready to start loft framing.
MASONS
touch-up glass block mortar joints @ unit entries


MATT'S for "notching" the aluminium mullion caps around the fasteners @ all entries


CARPENTERS kris & radek are installing clip angles to support loft framing. drywall is installed 1st to maintain 1h rating at demising wall


CARPENTERS
2x12 hemp fir joists are doubled (glued/nailed) to clear span the space and provide a stiff floor

CARPENTERS
joists are about ready for 3/4" sturdifloor plywood subfloor


CARPENTERS the lift becomes the plywood elevator

CARPENTERS tomek & tomek trim sturdifloor deck to curve



CARPENTERS deck is done, low 2x6 partition forms rail with the balance to be infilled with steel tube rail after carpet

ELECTRICIANS 1 1/4" conduit is used to feed circuit panels and pull communication wiring to the unit. This occupies the middle "pipe chase" layer on the masonry. The green vertical unistrut clamping system keeps things tidy. The electrical service is located behind the masonry wall


ELECTRICIANS pipe chase wall is complete. communications conduit is extended to the individual individual units

ELECTRICIANS
electrical panel wiring is being pulled back to the service



PLUMBING waste/vent piping (white PVC) occupies the middle layer. The top pipe (vent) needs to be at 42" which is below the bottom electical feeds

PLUMBING laundry box is being piped. No need for this with office users, but it's easier to do this now...building usage changes

PLUMBING water supplies for bathroom shower/tub are being installed


CARPENTERS
protruding skylight curbs are protected with plastic which is removed prior to starting roofing work. a 6" section of roofing was removed around the curb perimeter so the framing can sit directly against the existing wood deck. The balance of the existing roof membrane was
temporarily retained to keep the building dry


CARPENTERS tomek is removing the existing roof membrane inside the skylight prior to removing the roof deck

CARPENTERS removing the existing roof deck inside the skylight

CARPENTERS matt, kris and radek are laying out the roof flashing locations for the plumbing vent, unit furnaces and water heater. 3 holes/unit


CARPENTERS kris has cut the 3 holes and is building up the flashing height 4" to match the height of the polyiso roof insulation. joe hall, the roofing contractor is checking things out for his job next week

CARPENTERS build up done, flashings being installed


CARPENTERS
abandoned roof deck openings from a previous “incarnation” are patched to match the existing

NEW MANAGEMENT matt's lame excuse for abandoning his post. congrads to leane and madeline stryker berry born 11.7.09






Monday, October 19, 2009


SHOP(studios) 940 Pitner Evanston, IL 60202


PROJECT UPDATE (10.14.2009):

Signe, Matt and I started demolition at our latest adaptive re-use project, 940 PITNER on 8.8.09. The underground plumbing and concrete trades were quickly followed by the carpenters and masons. Mechanical trades to follow in the next few weeks then the new insulation/roofing system…WINTER is coming.

940 was last used as an automobile repair/paint shop. We are converting this building into 5 office RENTAL UNITS ranging in size from 975-1226 SF. The middle 3 units will have lofts and the front and rear units will be on a single level. Each will have a storefront entry and be similar in feeling and finish to our 12 unit project next door at 930 Pitner. We expect to attract “artistic professionals” as tenants as we have at another of our facilities, the STAMPfactory (19 units) at Dewey/Payne. Aggressive rents of $1,250 – $1,730 per month including property taxes make these spaces very attractive to start-ups and small local businesses. Occupancy will be spring 2010.

ANDY (ps: all the fotos below were taken in the last 45 days)


pre-demo...whata mess (looking east)

CONCRETE demolition is nearly complete. NEW underground plumbing to follow (looking east)







underground PLUMBING nearly complete. MATT & ALEX are doing a final check


CONCRETE
floor slab in bath area.ceramic tile will cover the mess

MASONS are preparing for one new entry opening. notice how the bricks are removed in a 45 degree pattern to follow the downward force of the brick above. we were able to re-use 3 other openings (looking west)

MASONS are infilling unused openings. brick cleaning will "blend" the color (west elevation)

CARPENTRY partition layout starts (looking west)

CARPENTRY skylight layout also starts. new curbs are cut to follow the roof slope. see next photo (looking west)


CARPENTRY skylight curbs are complete. new roof/insulation system will follow in about 3 weeks after mechanical systems roof penetrations are finalized (looking east)


CARPENTRY. tomek & tomek begin unit entry framing (looking west down walkway)

CARPENTRY. kris & radek frame unit interiors. notice opening on the left so units can be combined.

CARPENTRY bathroom & utility closet are being framed in unit 2


CARPENTRY. tomek is finishing unit demising partitions. all lumber is harvested from sustainable forests

WATER SERVICE excavation for new 1 ½” feed begins


WATER SERVICE an auguring installation technique is used requiring minimal street repair and traffic disruption (looking west from pitner)

WATER SERVICE new water tap (blue & red) has been made. auguring begins


MASONS install glass block @ unit entries

BOWSTRING TRUSS REPAIR demolition uncovered a problem requiring a bottom cord replacement in unit 1. Steel shoring is still in place @ panel points (truss member intersections).


MASONS install glass block @ unit entries…almost 100%


MATT & SIGNE don’t remember this wall being there?

andrew spatz (adas/spatz properties)


(O) 847.864.3100
(C) 847.971.3290
(F) 847.869.5647

(website)
Click here: adas spatz properties