Wednesday, June 13, 2018

wareHOUSE(2) 2113 greenleaf (PROJECT UPDATE) 6.14.2018


wareHOUSE(2)
2113 GREENLEAF
Evanston, Illinois 60201
adas/spatz properties
PROJECT UPDATE (06.14.2018):


This episodes focus is exclusively on the EXTERIOR SUN SCREENS and unit entry LOGGIA. These elements are primary to the projects exterior design. The aluminum tube/pipe armature was built in a local shop full size with some dimensions over 70'. Panels were then cut into 3 or 4 pieces, shipped to the jobsite and then re-assembled prior to erection. Once in place, the armatures are skinned with 1/8" solid and perforated aluminum panels depending on their facade location. All material, transport and labor was locally sourced. Aluminum is made from 90% recycled content and is 100% recyclable, thus is a very green/cost effective/low maintenance material.   

Concurrently, multiple trades continue the north to south rotation finishing their portion on the project and will be featured in a future project update shortly.


NEXT, exterior sun screens/unit entry loggia continue, site work + continuation of finishing the interiors.

…the end is near

andy




























Friday, April 13, 2018

warehouse(2) 2113 greenleaf (project update) 4.12.2018


wareHOUSE(2)
2113 GREENLEAF
Evanston, Illinois 60201
adas/spatz properties

PROJECT UPDATE (04.12.2018):


Concurrently, multiple trades continue the north to south rotation maintaining our project schedule. This project update groups our photos by trade to make the controlled chaos easier to follow.

- CARPETNTRY (cabinet installation, prep for all other trades)
- ORNAMENTAL IRON (completion of the steel stairs)
- PAINTING (priming, finished coat #1, spraying)
- CERAMIC TILE (bathroom wall tile & kitchen backsplash installation)
- HVAC (ductwork installation)
- FINISHED FLOORS (concrete floor prep, epoxy finished coating)


NEXT, exterior sun screens, site work + continuation of finishing the interiors with ELECTRICAL being added to the mix
…progress

andy


CARPENTRY: cabinet installation.
CARPENTRY: cabinet installation.
ORNAMENTAL IRON: matt checks layout.
ORNAMENTAL IRON: jose welds stair treads.
ORNAMENTAL IRON: ready for railings.
ORNAMENTAL IRON: railings installed in this unit. 
ORNAMENTAL IRON: railings being installed.
ORNAMENTAL IRON: railings installed on stair, wall and mezzanine.
LOFT VIEW to 1st level.
PAINTING: priming.
PAINTING: priming.
PAINTING: 1st finished coat. special colors for a special client.
PAINTING: marek readies trim for carpenters.
CERAMIC TILE: we have worked with arben over 20 years.
HVAC: ductwork installation in progress.
HVAC: ductwork installation in progress.
HVAC: ductwork installation in progress.
FINISHED FLOORS: step 1, concrete is thoroughly scrubbed. clemente & mario have been with us 15+ years.
FINISHED FLOORS: step 2, coat #1 of water based low VOC epoxy. 30 mils when completed.
FINISHED FLOORS: step 1,coat #1 completed.
PAINTING: lukasz takes a break from spraying the ceilings in the service corridor. we have a 15 year history. 

 FINISHED FLOORS: step 2, coat #1 of water based low VOC epoxy. 30 mils when completed.




Monday, February 19, 2018

wareHOUSE(2) 2113 greenleaf (PROJECT UPDATE) 2.19.2018



wareHOUSE(2)
2113 GREENLEAF
Evanston, Illinois 60201
adas/spatz properties

PROJECT UPDATE (02.19.2018):

INSULATION…done, DRYWALL has been installed and taping is 75% complete. PAINTING preparation/priming has begun at the north end and CERAMIC TILE begins in the next few days as will HVAC duct work hanging at the north end. The size of the project allows us to work from north to south condensing our timeline (thanks matt).

NEXT, cabinet delivery and installation
photos + video…progress

andy



INSULATION: a blown in blanked system is used in all 2x8 exterior walls. this coupled with 1.5" of polyiso rigid foam rates this assembly at r-49.
INSULATION: 1.5" (r-7.5" rigid insulation over concrete wall, blue), 8.75" (r-49 rigid assembly described above) and   7.25" sound batts in  the unit 2x8 demising walls.
DRYWALL: unit 15 is starting to take shape.

DRYWALL: the lift turns this "shape" into a one person job.

DRYWALL: unit 12 is read for taping.

DRYWALL: taping in progress in unit14.

DRYWALL: drywall being hung in unit 10 mezzanine.

DRYWALL: unit 9 is ready to tape.

DRYWALL: unit 11 looking east.

DRYWALL: unit 15 taping has received it's 3 coat of taping process...ready to sand.

DRYWALL: service corridor also underway.

DRYWALL: unit 7 at the south end being hung.

DRYWALL: unit 14 being sanded.

DRYWALL: the lift mitigates wear and tear on the body.

DRYWALL: unit 11 ready has been sanded...ready for the painter.

DRYWALL: unit 7 is ready to sand.

DRYWALL: units 10-11 are ready to sand.

PAINTING: lukasz & ted have prepped the metal deck in unit 13 and are spraying coat 1 of tinted primer.

PAINTING: unit 11 primed and looking good.

PAINTING: unit 15 is receiving first finish paint coat.

CABINETS: kris & hubert are inspecting the bathroom vanities prior to install.

MATT in the service corridor.